某矿过断层石门工程的数值模拟研究
Numerical Simulation Research of Crossway Project Acrossing Fault in a coal mine
基于某矿地应力测量成果,建立了过F10断层三种方案的石门工程地质模型,采用FLAC 3D有限差分软件分别进行模拟,得出了该石门的最佳方案,即选择最大水平主应力方向作为石门掘进方向、深度位置为"一水平",更有利于巷道支护,减少应力集中现象出现。实际工程位置宜选取在-450~-550m,布置在02~03勘探线之间,提出了施工、支护和防水建议。
Based on in-situ stress measuring results in a coal mine, three kinds of crossway geological model have been established by FLAC 3D numerical simulation. It is concluded that the best solution is selecting location, No.1 level and the orientation of maximum principal stress is the crossway's move towards. It's better to avoid stress concentration phenomenon appeared and support roadway easily. According to the actual project, selecting the location between -450 and -550 m and determining crossway is between 02 and 03 exploration line. Finally it puts forward suggestions on construction, support and waterproof.
鞠远江、葛明洋
矿山压力、矿山支护矿山建设、矿山设计矿山地质、矿山测量
地质工程地应力特征数值模拟石门工程
Geological EngineeringIn-situ stress characteristicsNumerical simulationCrossway project
鞠远江,葛明洋.某矿过断层石门工程的数值模拟研究[EB/OL].(2014-06-20)[2025-08-30].http://www.paper.edu.cn/releasepaper/content/201406-325.点此复制
评论