大型建设项目总进度目标论证研究—以昆明理工大学国际学术交流中心项目为例
Study on the demonstration of the progress goals in large-scale construction projects
本文以昆明理工大学国际学术交流中心项目为例,系统阐述了大型建设项目总进度目标论证的一般步骤,包括项目结构分解及关键工作分析、关键工作的持续时间估算、关键工作搭接与总进度纲要编制、总进度目标的优化和平衡等,并重点介绍了专家咨询法估算工作持续时间时确定权重的配对比较法。
his paper described the general steps of demonstration of the progress goals in Large-scale construction projects. As International Academic Exchange Center of Kunming University of Science and Technology for example, This paper described the work breakdown structure and the analysis of key work (sub), the key work of the estimated duration , key work of overlapping and the progress of the preparation of the outline, the goal of progress in the optimization and balance, and particularly introduce the method of matching comparative applied to decide the weight when estimating the duration of the work with the method of the expert advice.
张普伟、丁佳佳
建筑施工建筑基础科学建筑设计
建设项目项目进度配对比较法
building projectsprogress of the projectthe method of matching comparative
张普伟,丁佳佳.大型建设项目总进度目标论证研究—以昆明理工大学国际学术交流中心项目为例[EB/OL].(2008-10-10)[2025-08-18].http://www.paper.edu.cn/releasepaper/content/200810-175.点此复制
评论