本文结合LNG接收站水工模型试验,对LNG接收站取水口的水力特性进行研究。工程采用的钢管桩内取水设计方案在国内较为新颖,属于非常规取水结构。本文定量地分析水位变化、流速变化、不同泵型流道以及淹没深度变化对取水桩内流态的影响。其研究成果可为工程设计提供更为可靠的设计依据。

hrough hydraulic model test, the hydraulic characteristics of receiving station intake is researched in this paper. This project uses the design scheme of getting water from in steel pipe stake, which is more novel in China and belongs to the unconventional water withdrawal structure. the influences of change of water level ,flow rate,submerged depth as well as different pump channel type in steel pipe stake,are analysed in this article,which can provide more reliable basis for design of project.

雷兴春、郑亚军

水工结构水利工程基础科学

取水口水力特性水头损失水泵模型试验

intakehydraulic characteristicshead losspumpmodel test