子长选煤厂提高三产品旋流器的探索
Exploration of operational capacity of the three-product dense medium cyclone in Zichang coal preparation plant
子长选煤厂扩建改造后, 出现了三产品重介旋流器处理量偏低的严重问题,影响了选煤厂的正常生产,给选煤厂造成了一定的经济损失。文章讲述了三产品旋流器的分选原理及结构特点,分析了选煤厂重介旋流器处理量偏低的原因,采取了改进重介旋流器入料润湿方式和控制入料上限的措施,从而有效解决了这一困扰生产的问题,使旋流器的处理量达到设计要求,由原来的185t/h提高到280t/h,极大的提高了选煤厂的入洗能力,同时也解决了旋流器二段堵塞的现象,减少了工作时间,给企业带来良好的经济效益。
fter deforming and extension construction,the three-product dense medium cyclone performed a lower operational capacity in Zichang Coal Preparation Plant ,this affected the normal production of Coal Preparation Plant and caused some economic loss. In this article, separation principle and structure feature of three product dense medium cyclone were told,causes of a lower operational capacity was analysed.After taking measures to improve the wetting form and control the oversize of the feed of three product dense medium cyclone,the question was solved and the capacity rised greatly from 185t/h to 280t/h,meantime,the jam of cyclone solved, therefore working time was decreased and a good economic benefit to the enterprise.
王勃、孙再征、常发军
选矿
重介旋流器处理能力润湿
dense medium cycloneoperational capacitywetting
王勃,孙再征,常发军.子长选煤厂提高三产品旋流器的探索[EB/OL].(2010-10-20)[2025-08-10].http://www.paper.edu.cn/releasepaper/content/201010-327.点此复制
评论